Xinxiang City Zhenyuan Machinery Co., Ltd. Feeding equipment is a new device, in the production process in a timely, regular, and even keep the massive, granular materials evenly to the affected device to go up in the stone production line continue to feed crushing equipment, and materials for screening. It is widely used in mineral processing, abrasives, building materials, chemicals, ceramics, cement, metallurgy and other industries screening, crushing joint devices.
2013年9月8日星期日
Heavy plate feeder operation and maintenance and overhaul procedures
The operator should be familiar apron Vibrating feeder structure and application , each class should be checked before the operation plate feeder parts are normal, chain plate connecting
bolts are loose , no abnormal before starting operation . Here to introduce you to heavy plate Pan feeder in operation England note , and
Its maintenance and repair procedures.
1 Use the board in the chain should always maintain a certain thickness of material , generally not less than 460 mm . The state is not allowed to unload directly to the chain
plate discharge, when emptied can not be avoided when the chain plate before unloading Lay a layer of debris, to prevent the direct impact of the chain plate , when the bulk
material clogging
Is not allowed to use the form explosive discharge ;
(2) Install the rear plate feeder spout top to the distance between the top of the chain plate not less than two times the largest block of material , to ensure smooth flow of
materials to improve the service life of the chain plate . To avoid spills and the materials and materials generated by the friction caused by the sound baffles , guide plate
should be installed on both sides of the bezel with the chain plate
A gap left between 50-100 mm . The bottom edge of the guide plate from the surface of the chain plate maintained at 10-25 mm , to prevent material spills, tensioning device away
from the axis of the silo wall should leave some space , usually 350-500 mm , ease of maintenance disassembly ;
3 apron feeder chain pitch inside track pin bushing wear to greater than 7 mm , the sleeve should be transferred to a new angle or replace the chain ;
4 plate feeder disassembly expansion sets , first loosen all the screws , but do not all of the screws removed. Remove galvanized screws and washers , the removed screw into the
holes before the pressure in the auxiliary ring , gently tapping the screw head , so get moving expansion sets , then pull out the screws , expansion sleeve that is pulled along
Out ;
5 mounting plate feeder expansion sets , should the original installation of the joint surface clean , evenly coated with a thin layer lubricants ( excluding molybdenum
disulfide ) , the expansion sleeve screws with a torque wrench by diagonal cross evenly tighten ;
6 apron feeder unit bearing mounted head , the minimum clearance should ensure about 0.08 mm , radial clearance reduction in the amount of 0.09-0.11 mm can be. Rolling tail unit
should ensure that minimum clearance of about 0.055 mm , the radial decrease in the amount to between 0.06-0.07